Design for Woolsey Hall is under wayDesign for Woolsey Hall, the new building to house the W. Frank Barton School of Business, is under way. Researchers from the selected architectural team, GastingerWalker out of Kansas City + Gensler Chicago, were on campus in October to become more familiar with the current Barton School of Business facilities, observe how students, faculty and staff move through campus, and learn about the types of spaces that most resonate with our community.
A poster session was set up to get feedback from faculty, staff, and students about the types of spaces and activities they hope to see in the new building.
The architectural team was selected following interviews of a short list of firms provided by the State Building Advisory Commission. The selection committee consisted of staff from Wichita State University and the WSU Foundation, as well as the Office of Facilities and Property Management and the Kansas Board of Regents.
As promised, Wichita State University announced in April 2019 a plan to move forward
through budget reallocations and cuts to finance Woolsey Hall, a new business building,
and begin to meet other academic facilities’ needs identified in the March 2019 student
infrastructure referendum.
University officials respect to the results of the referendum, which students defeated
by 107 votes of nearly 3,500 votes cast. As a consequence of that vote, where student
fees will not be raised for these purposes, we’ve chosen a path that seeks the same
outcome: positioning WSU in a positive way to meet the academic infrastructure needs
of future generations of students.
To make these reallocations starting in FY 2020, we’re planning to use general use
sources of funding in positions and other budgeted items. When possible we will cover
these items by available restricted use funds, and in other cases they will be cut
from the general use budget.
The combined reallocations and cuts will generate resources to make an annual bond
payment of approximately $1.5 million, needed to raise $20 million dollars, the university’s
share of the building cost. Private gifts to the WSU Foundation will cover the remaining
$30 million dollars.
The numbers are still being finalized, but here’s roughly what we expect to reallocate:
We are also working on plans to move forward, though more slowly, on referendum priorities to upgrade other spaces in academic buildings. One of the least expensive and most needed of those is the Ablah Library enhanced 24-hour study space and restrooms. Construction began in fall 2019.
In summer 2020, we’d like to start working on other projects, such as renovating biology
labs and psychology and play therapy clinics. The money is expected to come from centralizing
shrinkage accounts, which is where vacant position salary dollars accumulate, and
from state funds for rehabilitation and repair, when appropriate.
We know these reallocations and cuts will be hard, as they will be permanent, since
the bond payment will run at least 25 years. Many departments and individuals will
feel these cuts, but this is the direction we need to take, based on the outcome of
the referendum and the university’s need to continue to evolve and grow.
Questions or comments? Email provost@wichita.edu.
The information on this page is accurate as of Nov. 4, 2019. Comment on this topic.
Wichita State University must continue to evolve and grow to fulfill its mission to be an essential educational, cultural and economic driver for Kansas. The new business building is a key part of those efforts and benefits the entire university by providing increased applied learning opportunities and enhanced engagement with the local business community. It is also central to WSU's long-term growth, because studies show new facilities of this type have a significant positive effect on enrollment. In addition, moving the Barton School of Business out of Clinton Hall makes possible the eventual renovation of that space for a consolidated student services hub right in the heart of campus.
From a financial standpoint, the reallocation was deemed the most palatable of the options left to the university after the referendum failed.
The university hopes to have all budgets finalized by the end of May.
The reallocations will take effect July 1, 2019, the start of the 2020 fiscal year.
The plan is focused on the Barton School of Business and units that have substantial revenue sources other than General Use funds (the revenue pool derived from the state of Kansas General Fund allocation plus tuition). The units chosen have greater flexibility in budgeting that may allow some line items to be covered by non-GU funds, minimizing the impact of the reallocation.
In most cases, positions will be shifted to non-GU sources of revenue. Cutting currently filled positions has not been proposed, however, a unit may choose to not fill a vacant position. The university is working with budget officers from departments across the university to help determine the best way to meet target numbers.
We expect that many of the university's campus improvement priorities will have later start dates. That means a slower overall pace of renovations, improvements and added services, but does not mean we'll be abandoning those priorities.
Since most positions and items will be covered by non-general use funding, WSU students should not see major impacts from the changes. It will mean that less investment in programming – financial support of academic and nonacademic student initiatives and activities -- will be possible, as there will be less non-general use funding available to do so.